DOI https://doi.org/10.36487/ACG_rep/1304_22_Dunn
Cite As:
Dunn, MJ 2013, 'Uncertainty in ground support design and implementation in underground mining', in Y Potvin & B Brady (eds),
Ground Support 2013: Proceedings of the Seventh International Symposium on Ground Support in Mining and Underground Construction, Australian Centre for Geomechanics, Perth, pp. 345-358,
https://doi.org/10.36487/ACG_rep/1304_22_Dunn
Abstract:
In underground mining, there are a number of uncertainties in the ground support design process and during implementation of ground support designs. The minimisation of geological uncertainty is one of the rock engineering principles outlined by Bieniawski (1992) and by Stacey (2004, 2009). Generally, there are two main types of uncertainty; uncertainty due to naturally variable phenomena in time or space and that due to lack of knowledge or understanding (Baecher and Christian, 2003). McMahon (1985) listed six types of geotechnical uncertainty: risk of encountering unknown geological conditions; risk of using incorrect geotechnical criteria; bias and/or variation in estimated design parameters is greater than anticipated; human error; design changes and excessive conservatism.
All of these types of uncertainty are encountered in the design of ground support. They occur in the form of uncertainties around: the design block size; loading conditions; spatial variability of ground conditions; rock mass strength; shear strength; discontinuity spacing; discontinuity orientations, etc. Uncertainty is not only present in the design of ground support but also in the implementation phase. This occurs in the form of variations in installation quality; adherence to patterns and spacing; human error in the application of the correct ground support standard; not identifying a change in ground conditions, etc.
Conventional deterministic and empirical design methods do not adequately cater for uncertainties in the design of ground support. Probabilistic design methods such as the Point Estimate Method and Monte Carlo Simulation can be applied to better understand the uncertainties in the design process. Limiting uncertainties in ground support implementation can be achieved by: training of operators and supervisors; good supervision of implementation; and a well-considered and managed quality control programme. It is important to feed the results from the quality control and monitoring programmes back into the design.
In this paper, the various uncertainties with ground support design and implementation will be reviewed and discussed in context of McMahon (1985) and Baecher and Christian (2003). The application of probabilistic design methods in ground support design and feedback of quality control data will be discussed.
References:
Baecher, G.B. and Christian, J.T. (2003) Reliability and Statistics in Geotechnical Engineering, Wiley, 618 p.
Barton, N., Lien, R. and Lunde, J. (1974) Engineering classification of rock masses for the design of rock support, Rock Mechanics, Vol. 6, pp. 189–236.
Beauchamp, K.J., Carvalho, J., Castro, L. and Morrison, D.M. (1998) Probabilistic Analysis for Ground Support for Underground Mines, Canadian Institute of Mining, Montreal.
Beck, D.A., Pfitzner, M.J., Arndt, S.M. and Fillery, B. (2009) Estimating rock mass properties and seismic response using higher order, discontinuous, Finite Element models, in Rock Engineering in Difficult Conditions, in Proceedings Third Canada‒U.S. Rock Mechanics Symposium and 20th Canadian Rock Mechanics Symposium, M. Diederichs and G. Grasselli (eds), 9‒15 May, Toronto, Canada, 12 p. (on CD‐ROM).
Bieniawski, Z.T. (1992) Principles of engineering design for rock mechanics, in Proceedings 33rd US Symposium on Rock Mechanics, J.R. Tillerson and W.R. Wawersik (eds), 3–5 June 1992, Santa Fe, USA, Balkema, Rotterdam, pp. 1,031–1,040.
Bieniawski, Z.T. (1976) Rock mass classifications in rock engineering, in Proceedings Symposium on Exploration for Rock Engineering, Z.T. Bieniawski (ed), Cape Town, South Africa, Balkema, Rotterdam, Vol. 1, pp. 97–106.
Brown, E.T. (2007) Block Caving Geomechanics, Second edition, JKMRC, Brisbane, 696 p.
Carter, T.G. and Miller, R.I. (1995) Crown-pillar risk assessment – planning aid for cost-effective mine closure remediation, Trans. IMM (Sect. A), 104, pp. A41–A57.
Esterhuizen, G.S. and Streuders, S.B. (1998) Rockfall hazard evaluation using probabilistic keyblock analysis, Journal of the South African Institute of Mining and Metallurgy, March/April 1998, pp. 59–63.
Esterhuizen, G.S. (1996) JBlock User’s Manual and Technical Reference.
Esterhuizen, G.S. (1993) Variability considerations in hard rock pillar design, in Proceedings Symposium on Rock Engineering problems related to Hard Rock Mining at Shallow to Intermediate depth, 4–5 March 1993, Rustenburg, South Africa, South African National Group on Rock Mechanics, South Africa, pp. 48–54.
Diederichs, M., Espley, S., Langille, C. and Hutchinson, D.J. (2000) A semi-empirical hazard assessment approach to wedge instability in underground mine openings, in Proceedings International Conference on Geotechnical and Geological Engineering, GeoEng 2000, 19–24 November 2000, Melbourne, Australia, Technomic Publishing, Lancaster.
Dunn, M.J. (2010) The application of probabilistic keyblock methods for support design in blocky rock masses, in Proceedings 2nd Australasian Ground Control in Mining Conference, P. Hagan and S. Saydam (eds), 23–24 November 2010, Sydney, Australia, The Australasian Institute of Mining and Metallurgy, Sydney, pp. 106–112.
Dunn, M.J., Earl, P. and Watson, J. (2008) Support design using probabilistic keyblock methods, in Proceedings 6th International Symposium on Ground Support in mining and civil engineering applications, T.R. Stacey and D.F. Malan (eds), 30 March–3 April 2008, Cape Town, South Africa, The Southern African Institute of Mining and Metallurgy, Johannesburg, pp. 623–636.
Goodman, R.E. and Shi, G. (1985) Block Theory and its Application in Rock Engineering, Prentice-Hall, 338 p.
Graf, C.C. and Basson, F.R.P. (2010) Managing Stress and Ground Condition Changes with Increasing Depth at Callie Underground Mine, in Proceedings 2nd Australasian Ground Control in Mining Conference, P. Hagan and S. Saydam (eds), 23–24 November 2010, Sydney, Australia, The Australasian Institute of Mining and Metallurgy, Sydney, pp. 106–112.
Grenon, M. and Hadjigeorgiou, J. (2003) Open stoping using 3D joint networks, Rock Mechanics and Rock Engineering, Vol. 36(3), pp. 183–208.
Hadjigeorgiou, J. (2012) Where do the data come from? In Proceedings Sixth International Seminar on Deep and High Stress Mining, Y. Potvin (ed), 28–30 March 2012, Perth, Australia, Australian Centre for Geomechanics, Perth, pp. 259–277.
Hadjigeorgiou, J. and Harrison, J.P. (2011) Uncertainty and Sources of Error in Rock Engineering, in Proceedings 12th ISRM International Congress on Rock Mechanics, Harmonising Rock Engineering and the Environment, Q. Qian and X. Zhou (eds), 18–21 October 2011, Beijing, China, CRC Press, Leiden, pp. 2,063–2,067.
Hoek, E. (1991) When is a design in rock engineering acceptable? Müller Lecture, in Proceedings 7th International Congress on Rock Mechanics, 16–20 September 1991, Aachen, Germany, Balkema, Rotterdam, Vol. 3, pp 1,485–1,497.
Harr, M.E. (1989) Probabilistic estimates for multivariate analysis, Applied Mathematical Modelling, Vol. 13.
Harr, M.E. (1987) Reliability based design in civil engineering, McGraw-Hill, New York, 290 p.
Hoek, E., Kaiser, P.K. and Bawden, W.F. (1995) Support of Underground Excavations in Hard Rock, Balkema, Rotterdam, 300 p.
Hutchinson, D.J. and Diederichs, M.S. (1996) Cabelbolting in Underground Mines, BiTech, 406 p.
Joughin, W.C., Swart, A.H. and Wesseloo, J. (2000) Risk based chromitite pillar design - Part 2: Non-linear modelling, in Proceedings South African National Institute of Rock Engineers Symposium: Keeping it in the Bushveld and Advances in Support Technology, 10–11 October 2000, Rustenburg, South Africa, South African National Institute of Rock Engineering.
Kiureghian, A.D. and Ditlevsen, O. (2009) Aleatory or epistemic? Does it matter? Structural Safety, 31, pp. 105–112.
Lunder, J. (1994) Hard rock Pillar strength estimation an applied empirical approach, MSc thesis (unpublished), University of British Columbia, Canada.
McMahon, B.K. (1985) Geotechnical design in the face of uncertainty, Austalian Geomechanics Society E.H. Davis Memorial Lecture.
Peck, R.B. (1969) Advantages and Limitations of the Observational Method in Applied Soil Mechanics, Ninth Rankine Lecture, Geotechnique 19, No. 2, pp. 171–187.
Pells, P.J.N. (2008) Assessing parameters for computations in rock mechanics, in Proceedings First Southern Hemisphere International Rock Mechanics Symposium (SHIRMS), Y. Potvin, J. Carter, A. Dyskin and R. Jeffrey (eds), Vol. 1 – Mining and Civil, 16‒19 September 2008, Perth, Australia, Australian Centre for Geomechanics, Perth, pp. 39–54.
Pine, R. and Thin, I. (1993) Probabilistic risk assessment in mine pillar design, in Proceedings International Congress on Mine Design, Innovative Mine Design for the 21st Century, W.F. Bawden and J.F. Archibald (eds), 23–26 August 1993, Kingston, Canada, Balkema, Rottedam, pp. 363–373.
Potvin, Y. and Nedin, P. (2003) Management of Rockfall Risks in Underground Metalliferous Mines, Minerals Council of Australia.
Priest, S.D. and Brown, E.T. (1983) Probabilistic stability analysis of variable rock slopes, Transactions of the Institution of Mining and Metallurgy, Section A: Mining Industry, IMM, Vol. 92, January 1983, pp. A1‒A12.
Ranasooriya, J. and Nikraz, H. (2008) Tetrahedral rock wedge stability under empirically derived support, in Proceedings First Southern Hemisphere International Rock Mechanics Symposium (SHIRMS), Y. Potvin, J. Carter, A. Dyskin and R. Jeffrey (eds), Vol. 1 – Mining and Civil, 16‒19 September 2008, Perth, Australia, Australian Centre for Geomechanics, Perth, pp. 619−632.
Reusch, F. and Beck, D. (2007) Simulating Shaft and Crusher Damage in Deep Mines, in Proceedings Fourth International Seminar on Deep and High Stress Mining (Deep Mining 07), Y. Potvin (ed), 7‒9 November 2007, Perth, Australia, Australian Centre for Geomechanics, Perth, pp. 65–79.
Stacey, T.R. (2009) Design—a strategic issue, The Southern African Institute of Mining and Metallurgy, Vol. 109, pp. 157–162.
Stacey, T.R. (2008) Are Design Codes Appropriate in Mining Rock Engineering?, in Proceedings First Southern Hemisphere International Rock Mechanics Symposium (SHIRMS), Y. Potvin, J. Carter, A. Dyskin and R. Jeffrey (eds), Vol. 1 – Mining and Civil, 16‒19 September 2009, Perth, Australia, Australian Centre for Geomechanics, Perth, pp. 129–136.
Stacey, T.R. (2004) The link between the design process in rock engineering and the code of practice to combat rock fall and rockburst accidents, The Journal of The South African Institute of Mining and Metallurgy, pp. 29–34.
Szwedzicki, T. (2004) Quality in ground support management, in Proceedings Fifth International Symposium on Ground Support, Ground Support in Mining and Underground Construction, E. Villaescusa and Y. Potvin (eds), 28‒30 September 2004, Perth, Australia, Balkema, Rotterdam, pp. 483–489.
Tapia, A., Contreras, L.F., Jefferies, M. and Steffen, O. (2007) Risk Evaluation of Slope Failure at the Chuquicamata Mine, in Proceedings International Symposium on Rock Slope Stability in Open Pit Mining and Civil Engineering (Slope07), Y. Potvin (ed), 12‒14 September 2007, Perth, Western Australia, Australian Centre for Geomechanics, Perth, pp. 477–495.
Thompson, A.G. and Windsor, C.R. (2007) Block formation around excavations using deterministic and probabilistic methods, in Proceedings 11th ISRM Conference, The Second Half Century of Rock Mechanics, 9–13 July 2007, Lisbon, Portugal, Taylor & Francis Group, London, Vol.1, pp. 183–186.
Tyler, D.B., Trueman, R. and Pine, R.J. (1991) Rockbolt support design using a probabilistic method of key block analysis, in Proceedings 32nd US Symposium on Rock Mechanics, 10–12 July 1991, Norman, Oklahoma, Balkema, Rotterdam, pp. 1,037–1,047.
Valley, B., Kaiser, P.K. and Duff, D. (2010) Consideration of uncertainty in modelling the behaviour of underground excavations, in Proceedings Fifth International Seminar on Deep and High Stress Mining (Deep Mining 2010), M. Van Sint Jan and Y. Potvin (eds), 6–8 October 2010, Santiago, Chile, Australian Centre for Geomechanics, Perth, pp. 423–436.
Wesseloo, J. and Read, J. (2009) Acceptance criteria, Guidelines for Open Pit slope Design, P. Stacey and J. Read (eds) CSIRO, Australia, pp. 221–236.
Wesseloo, J. and Swart, A.H. (2000) Risk based chromitite pillar design - Part 1: Application of locally empirically derived pillar formula, in Proceedings South African National Institute of Rock Engineers Symposium: Keeping it in the Bushveld and Advances in Support Technology, 10–11 October 2000, Rustenburg, South Africa, South African National Institute of Rock Engineering.
Wiles, T.D. (2006) Reliability of numerical modelling predictions, International Journal of Rock Mechanics and Mining Sciences, Vol. 43, pp. 454–472.
Windsor, C.R. (1999) Systematic design of reinforcement and support schemes for excavations in jointed rock, in Proceedings International Symposium on Ground Support and Reinforcement Practice in Mining, E. Villaescusa, C.R. Windsor, A.G. Thompson (eds), 15–17 March 1999, Kalgoorlie, Western Australia, Balkema, Rotterdam, pp. 35–58.