DOI https://doi.org/10.36487/ACG_rep/1608_20_Defferrard
Cite As:
Defferrard, PL, Rohde, TK & Lord, M 2016, 'Leading practice store and release cover trials for a tailings storage facility at Century mine', in AB Fourie & M Tibbett (eds),
Mine Closure 2016: Proceedings of the 11th International Conference on Mine Closure, Australian Centre for Geomechanics, Perth, pp. 291-304,
https://doi.org/10.36487/ACG_rep/1608_20_Defferrard
Abstract:
A store and release cover that is designed (the cover) to limit the release of sulphate salts and metals (the potential contamination) from acid forming tailings is site specific; being a function, among other factors, of the borrow materials available, tailings deposition method, and the climatic setting. Three experimental cover trials, each a 75 × 75 m square were developed and constructed on the tailings storage facility at MMG (Minerals and Metals Group) Century mine in the semi-arid Northwest Queensland. The covers rely on the storage of rainfall during the wet season and its release during the dry season through evapotranspiration. Covers typically comprises of a compacted fine-grained reduced permeability layer (RPL) of compacted clay overlain by a significant thickness of loose rock and soil (rock mulch). At the mine there is a paucity of fine-grained material for the RPL, this may be overcome by using mixtures of coarse and fined grained soil and rock (the mixtures). The cover trials have been designed to test three potential RPL mixtures which include minus 10 mm crusher dust conditioned with bentonite, a geo-synthetic clay liner placed between an upper and lower layer of minus 10 mm crusher dust, and minus 10 mm crusher dust conditioned with an extra 15 to 30% fines (passing 0.075 mm). All three cover trials have been enhanced by the addition of a capillary break (CB) layer directly above the tailings. The purpose of the CB is to stop the vertical rise of potential contamination from reaching the top layer of the cover, which is rock mulch. The performance of the cover trials is being monitored by instrumentation, including volumetric water content and matric suction sensors, a weather station capable of estimating evapotranspiration and lysimeters to measure percolation (deep infiltration) through the base of the cover. The instrumentation allows for direct measurement of infiltration into the cover, storage of rainfall and percolation through the base of the cover. The paper describes the cover trials construction, instrumentation and monitoring data from the past two years.
Keywords: tailings, cover, instumentation, Century, rehabilitation
References:
Buckley, J, Gates, WP, Gibbs, D, Gassner, F 2010, ‘Forensic Examination of Field GCL Performance in Landfill Capping and Mining Containment Applications’, in Proceeding of 3rd International Symposium on Geo synthetic Clay Liners, Wursburg, Germany.
Campbell Scientific Inc. 2000, Online Estimation of Grass Reference Evapotranspiration with the Campbell Scientific Automated Weather Station.
Dames & Moore 1994, The Century Project Draft Impact Assessment Study Report, vol. 3.
Defferrard, PL, Rohde, TK & Lord, M, 2015, ‘Instrumentation and early monitoring results of the South Waste Rock Dump at Century mine’, in AB Fourie, M Tibbett, L Swatsky & D van Zyl (eds), Proceedings of the 10th International Conference on Mine Closure, infoMine, pp. 917–928.
Defferrard, PL, Rohde, TK & Milsom, BJ 2014, ‘Performance of a cover on a bulk sample tailings dam at Century Mine’, in Proceedings of 8th Australian Acid and Metalliferrous Drainage Conference, Adelaide.
DITR (Department of Industry and Tourism) 2007, ‘Managing Acid and Metalliferous Drainage’, in Leading Practice Sustainable Development Program for the Mining Industry, DITR, Australian Government, Canberra.
EGi (Environmental Geochemistry International Pty Ltd) 1998, Pasminco Century Project Assessment of acid forming characteristics and metals leaching behaviour.
INAP (The International Network for Acid Prevention) 2009, Global Acid Rock Drainage Guide.
Reid, P 2012, Preliminary Concept Design of Cover Systems for the TSF, Rev B, ATC Williams Pty Ltd.
Rohde, TK 2013, Century Mine TSF Cover Trials Design and Construction Report, Rev A, EMGA Mitchell McLennan.
Rohde, TK 2014, Bulk sample tailings dam cover performance, Rev B, EMGA Mitchell McLennan.