Authors: Lyle, RR


DOI https://doi.org/10.36487/ACG_rep/1710_47_Lyle

Cite As:
Lyle, RR 2017, 'Considerations for large-diameter raiseboring', in M Hudyma & Y Potvin (eds), UMT 2017: Proceedings of the First International Conference on Underground Mining Technology, Australian Centre for Geomechanics, Perth, pp. 581-595, https://doi.org/10.36487/ACG_rep/1710_47_Lyle

Download citation as:   ris   bibtex   endnote   text   Zotero


Abstract:
For over 50 years, raisebore drilling technology has been successfully employed for vertical mine development in mines around the world. In the early days, raiseboring was limited to small-diameter (< 2 m) raises; but with time the method has evolved so that boreholes greater than 5 m are now routinely completed without incident. One important evolution is the Rotary Vertical Drilling System (RVDS) to maintain verticality of boreholes. This technology enables the effective development of hoisting shafts using accurately controlled vertical raisebored excavations. Mine planners must now consider using raiseboring techniques not only for small-diameter raises, but for largediameter vertical development, including ventilation, secondary egress and hoisting shafts. This paper provides insight into the important considerations for large-diameter raiseboring projects. This includes an examination of methods to assess geotechnical risk for large-diameter raiseboring projects, including the commonly employed McCracken and Stacy (1989) method. Examples of recent, prominent large-diameter raiseboring projects are also profiled to show the diverse range of projects which have been able to take advantage of modern raisebore technology.

Keywords: vertical mine development, raiseboring, mine planning, borehole hoisting

References:
Barton, N, Lien, R & Lunde, J 1974, ‘Engineering classification of rock masses for the design of tunnel support’, Rock Mechanics, vol. 6, pp. 189-236.
Bertuzzi, R & Wallis, J 2008, ‘Rock mass classification is only part of the answer to assess raise boring’, Proceedings of the 10th AusIMM Underground Operators’ Conference, The Australasian Institute of Mining and Metallurgy, Melbourne, pp. 191–198.
Bieniawski, ZT 1989, Engineering Rock Mass Classifications, John Wiley & Sons, New York.
Coombes, BM, Lee, MF & Peck, WA 2011, ‘Improving raisebore stability assessments and risk’, Proceedings of the 2011 Canadian Institute of Mining, Metallurgy and Petroleum Conference and Exhibition, Canadian Institute of Mining, Metallurgy and Petroleum, Westmount.
Dengler, WR & Brown, RS 1976, ‘Borehole hoisting for shaft sinking and development at Brunswick Mining and Smelting Corporation Limited, Bathurst, New Brunswick’, in R Robbins & R Conlon (eds), Proceedings of the 1976 Rapid Excavation and Tunnelling Conference, Society of Mining Engineers of the American Institute of Mining, Metallurgical, and Petroleum, New York. pp. 169–181.
Ferreira, PH 2005, ‘Mechanised mine development utilising rock cutting and boring through raise and blind boring techniques’, Proceedings of the Third Southern African Conference Base Metals, Southern African Institute of Mining and Metallurgy, Johannesburg, pp. 297–313.
Goodman, WM, Plumeau, DB, Voigt, JO & Gnage, DJ, 2009, ‘The history of room and pillar salt mines in New York State’, in S Zuoliang (ed.), Proceedings of the 9th International Symposium on Salt, vol. 2, Gold Wall Press, Beijing, pp. 1239–1248.
Harrison, GP, Green, NE & Bennett, WE 1972, ‘Some aspects of the art of raise boring’, in K Lane & L Garfield (eds), Proceedings of the 1972 Rapid Excavation and Tunnelling Conference, Society of Mining Engineers of the American Institute of Mining, Metallurgical, and Petroleum, New York, pp. 1161–1183.
Hudd, PS & Martin, D 2010, ‘Large diameter raise boring in hard rock – an overview, its applications and considerations’, Proceedings of the 2010 Canadian Institute of Mining, Metallurgy and Petroleum Conference and Exhibition, Canadian Institute of Mining, Metallurgy and Petroleum, Westmount.
Hudd, PS, Guimond, L & Bartlett, R 2014, ‘The successful design and construction of an 8,000 tpd production hoisting facility using a large diameter raise bored shaft’, Proceedings of the 2014 Canadian Institute of Mining, Metallurgy and Petroleum Conference and Exhibition, Canadian Institute of Mining, Metallurgy and Petroleum, Westmount.
Hutchinson, DJ & Diederichs, MS 1996, Cablebolting in Underground Mines, BiTech Publications, Vancouver.
James, N 2017, ‘Completion of Mindola shaft expected in 2019’, Mining Weekly, Creamer Media, Johannesburg, viewed 26 June 2017,
Lauffer, H 1988, ‘Zur Gebirgsklassifizierung bei Frasvortrieben’, Felsbau, vol. 6, no. 3, pp. 137–149.
Martin, DG, Hunt, R & Price Jones, A 2012, ‘New opportunities for mine planners – large diameter borehole hoisting systems’, Proceedings of the Third International Conference on Shaft Design and Construction, Institute of Materials, Minerals and Mining, London.
McCracken, A & Stacey TR 1989, ‘Geotechnical risk assessment for large-diameter raise-bored shafts’, Proceedings of the Second International Conference on Shaft Design and Construction, Institute of Materials, Minerals and Mining, London.
McGuire, C, Witow, D & Connors, C 2016, ‘Operating and maintenance experience for a mechanized raise climber in a metal mining egress application’, Proceedings of the 2016 Maintenance, Engineering and Reliability/Mine Operators (MEMO) Conference, Canadian Institute of Mining, Metallurgy and Petroleum, Westmount.
Nadon, MR & Kelly, MJ 1991, ‘Bore or blast – Alimak raising and raise boring which method for what conditions’, Engineering and Mining Journal, July 1991, pp. 34–36.
New South Wales Mine Safety 2013, Guideline for Raiseboring Operations, NSW Mine Safety, Sydney.
Oosthuizen, M 2004, ‘Large diameter vertical raise drilling and shaft boring techniques an alternative to conventional shaft sinking techniques’, Proceedings of the 2004 South African Institute of Rock Engineering Symposium, South African Institute of Rock Engineering, Stilfontein, pp. 149–163.
O’Toole, D & Sidea, D 2005, ‘Recent development in Australian shaft excavation practice – raise bored shafts in highly stressed rock’, Proceedings of the 9th AusIMM Underground Operators’ Conference, The Australasian Institute of Mining and Metallurgy, Melbourne, pp. 29–32.
Peck, WA & Lee, MF 2007, ‘Application of the Q-System to Australian underground metal mines’, in C Mark, R Pakalnis & R Tuchman (eds), Proceedings of the International Workshop on Rock Mass Classification in Underground Mining, National Institute for Occupational Safety and Health, Cincinnati, pp. 129–140.
Peck, WA & Lee MF 2008, ‘Stability of raise bored shafts in Australian mines’, in Proceedings of the 13th Australian Tunnelling Conference, The Australasian Institute of Mining and Metallurgy, Melbourne, pp. 331–337.
Peck, WA, Coombes, B & Lee MF 2011, ‘Fine-tuning raisebore stability assessments and risk’, Proceedings of the 11th AusIMM Underground Operators’ Conference, The Australasian Institute of Mining and Metallurgy, Melbourne, pp. 215–226.
Schrami, E & Schimper 2002, ‘Emergency egress/ventilation raise innovations in directional raise boring & remote shotcrete application’, Proceedings of the 2002 Canadian Institute of Mining, Metallurgy and Petroleum Conference and Exhibition, Canadian Institute of Mining, Metallurgy and Petroleum, Westmount.
Sidea, D & Pfitzner, M 2012, ‘Raiseboring… how well do you know your rocks’, presented at Vertical Development Workshop, Eastern Australia Ground Control Group, Hobart.
Sidler, V 2014, ‘Mopani Deeps reaches new heights at greater depths’, Mining Review Africa, no. 3, pp. 32–34.
Stack, B 1982, Handbook of Mining and Tunnelling Machinery, John Wiley & Sons, Chichester.
Stacy, TR & Harte, ND 1989, ‘Deep level raise boring – prediction of rock problems’, in V Maury & D Fourmaintraux (eds), Rock at Great Depth, A.A. Balkema, Rotterdam, pp. 583–588.




© Copyright 2024, Australian Centre for Geomechanics (ACG), The University of Western Australia. All rights reserved.
View copyright/legal information
Please direct any queries or error reports to repository-acg@uwa.edu.au