Authors: Barrera, S; Engels, J

Open access courtesy of:

DOI https://doi.org/10.36487/ACG_rep/1805_02_Barrera

Cite As:
Barrera, S & Engels, J 2018, 'High-density thickening for large production rates: main challenges', in RJ Jewell & AB Fourie (eds), Paste 2018: Proceedings of the 21st International Seminar on Paste and Thickened Tailings, Australian Centre for Geomechanics, Perth, pp. 35-42, https://doi.org/10.36487/ACG_rep/1805_02_Barrera

Download citation as:   ris   bibtex   endnote   text   Zotero


Abstract:
It has been apparent for some time that for large production rates where high-density thickened tailings disposal is considered (e.g. Minera Centinela and Toromocho), significant challenges have been observed to reach the design underflow solids concentration. Many possible explanations have been proposed and at the 19th International Seminar on Paste and Thickened Tailings a panel discussion was held addressing this problem in detail. Usually the issue is a combination of operational parameters resulting in variable performance of an industrial thickener. The purpose of this paper is to review and discuss the views raised in the panel discussion as indicated above, as well as visions/experiences on control and operational management of tailings thickeners for recent cases.

Keywords: thickening, thickener, operational control, panel discussion

References:
Caro, G, Schoenbrunn, F, Becerra, M & Kujawa, C 2016, Challenges in Implementation of Highly Thickened Tailings Technology in Large Production Rates, in S Barrera (ed.), 19th International Seminar on Paste and Thickened Tailings edited panel transcription,
Gaete, S 2014, ‘Applying large-scale thickened tailings technology on the sulfide line at Minera Centinela’, in S Barrera (ed.), Proceedings of the 2nd International Seminar on Tailings Management, Gecamin, Santiago.
Gaete, S & Bello, F 2013, ‘Experience with the thickening and discharge of high-density tailings – Minera Esperanza’, in S Barrera, M Niederhauser, G Shaw, D van Zyl and W Wilson (eds), Proceedings of the 1st International Seminar on Tailings Management, Gecamin, Santiago.
Gaete, S, Bello, F, Engels, J & McPhail, GI 2014, ‘Thickening and deposition trials: laboratory through to industrial scale – Minera Esperanza’, in RJ Jewell, AB Fourie, PS Wells and D van Zyl (eds), Proceedings of the 17th International Seminar on Paste and Thickened Tailings, InfoMine Inc., Vancouver, pp. 381–392.
McNamara, L, Khoshniaz, N & Hashemi, S 2011, ‘The Sarcheshmeh thickened tailings disposal project’, in RJ Jewell & AB Fourie (eds.), Proceedings of the 14th International Seminar on Paste and Thickened Tailings, Australian Centre for Geomechanics, Perth, pp. 237–244.
Paterson, AJC 2006, ‘Rheology control of paste and thickened tailings systems’, in RJ Jewell, S Lawson and P Newman (eds), Proceedings of the Ninth International Seminar on Paste and Thickened Tailings, Australian Centre for Geomechanics, Perth, pp. 47–56.
Schoenbrunn, F, Niederhauser, M & Baczek, F 2009, ‘Paste thickening of tailings: Process and equipment design fundamentals relative to deposition goals’, in M Deepak, PR Taylor, E Spiller and M LeVier (eds), Recent Advances in Mineral Processing Plant Design, Society for Mining, Metallurgy & Exploration, Littleton, pp. 455–465.
Thiele, C & Parraguez, L 2011, ‘Presentación, Minera Esperanza’, Seminario de Relaves en Pasta, presentation, viewed 5 February 2018,