Authors: Ross, IT

Open access courtesy of:

DOI https://doi.org/10.36487/ACG_rep/1815_36_Ross

Cite As:
Ross, IT 2018, 'Benchmarking and its application for caving projects', in Y Potvin & J Jakubec (eds), Caving 2018: Proceedings of the Fourth International Symposium on Block and Sublevel Caving, Australian Centre for Geomechanics, Perth, pp. 473-486, https://doi.org/10.36487/ACG_rep/1815_36_Ross

Download citation as:   ris   bibtex   endnote   text   Zotero


Abstract:
The process of benchmarking is commonly used when developing mining projects. As new projects come under scrutiny during the evaluation process, the key drivers, such as development advance rate, drawpoint construction and rate of caving or production ramp-up are, or should be, critically examined. However, with a limited pool of block/panel caving projects, is the process of benchmarking an appropriate tool to justify significant expenditure? This paper discusses some of the benefits and limitations of benchmarking and highlights some of the issues around establishing the true values ascribed to the parameters. It also highlights some common issues associated with comparing data from different mines.

Keywords: benchmarking, block caving, benefits, limitations

References:
Araneda, O & Sougarret, A 2008, ‘Lessons learned in cave mining at the El Teniente mine over the period1997-2007’, Proceedings of MassMin 2008, Luleå University of Technology, Luleå, pp. 43–52.
Brannon, C, Firdausi, H, Pascoe, N & Yuniar, A 2016, ‘Development and construction update of the Grasberg Block Cave mine’ Proceedings of MassMin 2016, The Australasian Institute of Mining and Metallurgy, Melbourne, pp. 625–633.
Brown, ET 2000, Block Caving Geomechanics, Julius Kruttschnitt Mineral Research Centre, Brisbane, pp. 126–138.
Casten, T, Rachmad, L, Arkadius, T, Osborne, K & Johnson, M 2008, ‘PT Freeport Indonesia’s Deep Ore Zone mine – expanding to 80,000 tonnes per day’, Proceedings of MassMin 2008, Luleå University of Technology, Luleå, pp. 265–274.
Catalan, A, Dunstan, G, Morgan, M, Green, S, Jorquera, M & Thornhill, T 2012, ‘An “intensive” preconditioning methodology developed for the Cadia East panel cave project, NSW, Australia’, Proceedings of MassMin 2012, Canadian Institute of Mining, Metallurgy and Petroleum, Westmount.
Flores, G & Karsulovic, A 2000, Geotechnical Guidelines for a Transition From Open Cut to Underground Mining: Benchmarking Report, report to the International Caving Study II, Julius Kruttschnitt Mineral Research Centre, Brisbane.
Glazer, S & Hepworth, N 2004, ‘Seismic monitoring of block cave crown pillar – Palabora Mining Company, RSA’, in A Karzulovic & MA Alfaro (eds), Proceedings of MassMin 2004, Instituto de Ingenieros de Chile, Santiago, pp. 565–569.
Hudyma, M, Potvin, Y & Allison, D 2007, ‘Seismic monitoring of the Northparkes Lift 2 block cave – part 2 production caving’, Proceedings of the 1st International Symposium on Block and Sub-Level Caving Cave Mining, The Southern African Institute of Mining and Metallurgy, Johannesburg, pp. 303–334.
Laubscher, D 2000, Block Caving Manual, report to the International Caving Study, Julius Kruttschnitt Mineral Research Centre and Itasca Consulting Group Inc., Brisbane, p. 16.
Lett, JL & Capes, GW 2012, ‘Characterisation of caving and subsidence for operational enhancements at the Newcrest Ridgeway gold mine’, Proceedings of MassMin 2012, Canadian Institute of Mining, Metallurgy and Petroleum, Westmount.
Ross, I 2004, ‘Northparkes Lift 2 development’, Proceedings of the Innovative Mineral Developments Symposium, Australasian Institute of Mining and Metallurgy, Melbourne, pp. 53–69.
Ross, I 2008, ‘Northparkes E26 Lift 2 Block Cave – a case study’, Proceedings MassMin 2008, Luleå University of Technology, Luleå, pp. 25–34.
Ross, I 2014, ‘Development – back to basics’, Proceedings of the 12th Underground Operators Conference, The Australasian Institute of Mining and Metallurgy, Melbourne, pp. 67–73.
Ross, I & deWolfe, V 2016, ’Supercaves – benefits, considerations and risks’, Proceedings of MassMin 2016, The Australasian Institute of Mining and Metallurgy, Melbourne, pp. 51–58.
Stewart, CA & Butcher, RJ 2016, ‘Block cave evaluation’, Proceedings of MassMin 2016, The Australasian Institute of Mining and Metallurgy, Melbourne, pp. 809–815.
Silveira, A 2004, ‘Undercutting at E26 Lift 2 Northparkes’, Proceedings of MassMin 2004, Instituto de Ingenieros de Chile, Santiago, pp. 410–414.
Tota, E 1997, ‘Northparkes mines – new performance benchmarks for underground mining’, Proceedings of the AusIMM Annual Conference, The Australasian Institute of Mining and Metallurgy, Melbourne, pp. 57–64.
Whiteman, D, Talu, S, Wilson, M, Watt, G, van AS, A & Kuiper, P 2016, ‘Cave tracker flow monitoring system installation at Argyle Diamond Mine’, Proceedings of MassMin 2016, The Australasian Institute of Mining and Metallurgy, Melbourne,
pp. 479–488.




© Copyright 2024, Australian Centre for Geomechanics (ACG), The University of Western Australia. All rights reserved.
View copyright/legal information
Please direct any queries or error reports to repository-acg@uwa.edu.au