Authors: Murphy, DP; Fromm, J; Bairstow, R; Meunier, D

Open access courtesy of:

DOI https://doi.org/10.36487/ACG_rep/1915_64_Murphy

Cite As:
Murphy, DP, Fromm, J, Bairstow, R & Meunier, D 2019, 'A repurposing framework for alignment of regional development and mine closure', in AB Fourie & M Tibbett (eds), Mine Closure 2019: Proceedings of the 13th International Conference on Mine Closure, Australian Centre for Geomechanics, Perth, pp. 789-802, https://doi.org/10.36487/ACG_rep/1915_64_Murphy

Download citation as:   ris   bibtex   endnote   text   Zotero


Abstract:
In response to the challenges of population growth and associated economic sustainability, Australian governments are moving towards more structured and coordinated approaches to regional development. The Pilbara Regional Investment Blueprint(Pilbara Blueprint), developed by the Pilbara Development Commission (Commission), establishes a vision for the region that seeks diverse, innovative and resilient commercial opportunities that are underpinned by capability development, investment capture and fostering growth, as well as maintaining a strong resources and energy industry. Key challenges for the achievement of this vision include complex planning and regulatory processes, as well as competition for productive land. Concurrently, the modern Australian mining and energy industry is nearing maturity, with an increasing number of operations approaching closure and providing opportunity for the consideration of repurposing mined land and associated assets for productive economic use. Although good examples of mine repurposing exist at both the global and national levels, current mine closure planning practices within both government and industry do not readily support or encourage repurposing as a beneficial outcome. The Commission has therefore engaged with government and industry stakeholders to develop a framework that aligns the objectives of minimising post-closure mining liability and achieving sustainable regional development, and that presents a unique opportunity to shift the current mine closure paradigm. Specifically, the Commission is building from existing land access and tenure frameworks to enhance existing transformational opportunities within the Pilbara, including renewable power generation, irrigated agriculture and tourism. This paper presents the proposed repurposing framework and discusses the process of stakeholder engagement, ongoing challenges to implementation and opportunities for proof of concept.

Keywords: relinquishment, repurposing, Pilbara Blueprint, regional development, Pilbara

References:
Australian Bureau of Statistics 2013, A Review of Regional Development Australia Committee Regional Plans, viewed 24 July 2016,
Butler, H & Bentel, GM 2011, ‘Mine relinquishment – process and learnings’, in AB Fourie, M Tibbett & A Beersing (eds), Proceedings of the Sixth International Conference on Mine Closure, vol. 2, Australian Centre for Geomechanics, Perth, pp. 3–11.
Commonwealth of Australia 2019, Rehabilitation of Mining and Resources Projects and Power Station Ash Dams as it Relates to Commonwealth Responsibilities, Environment and Communications References Committee, Canberra, viewed 24 March 2109,
Department of Lands 2016, Land Tenure Pathway for Irrigated Agriculture – Application Guidelines, viewed 9 July 2019,
Department of Mines and Petroleum & Environmental Protection Authority 2015, Guidelines for the Preparation of Mine Closure Plans, Perth, viewed 15 August 2015,
Department of Primary Industries and Regional Development 2017, Growing the Pilbara: A Prefeasibility Assessment of the Potential for Irrigated Agriculture Development, viewed 23 August 2018,
Department of Water 2013, Strategic Policy 2.09: Use of Mine Dewatering Surplus, Perth, viewed 24 August 2018,
Field, G & Harold, M 2013, Development of Beneficial use Solutions for Surplus Water from Marandoo Mine: Lessons learned, viewed 12 March 2017,
GHD 2015, Economic Analysis of Irrigated Agriculture Development Options for the Pilbara, viewed 24 August 20198,
Harvey, BE 2016, ‘The Eye of the Beholder - Utility and Beauty in Mine Closure', in AB Fourie & M Tibbett (eds), Proceedings of the 11th International Conference on Mine Closure, Australia Centre for Geomechanics, Perth, pp. 17–24.
Heyes, J, Murphy, D, Foster, S & White, S 2018, ‘What comes after mining? How regulatory frameworks can enable creativity’, in C Drebenstedt, F von Bismark, AB Fourie & M Tibbett (eds), Proceedings of the 11th International Conference on Mine Closure, Technical University Bergakademie Freiberg, Freiberg, pp. 173–182.
Jacobs 2018, Pilbara Irrigated Agriculture Feasibility Study: Preliminary Business Case for Investment, viewed 24 August 2018,
Johnston, SL & Wright, AH 2003, Mine Void Water Resource Issues in Western Australia, Water and Rivers Commission Hydrogeological Record Series Report No. HG 9, viewed 12 March 2017,
Kumar, RN, McCullough, CD & Lund, MA 2009, ‘Water resources in Australian mine pit lakes’, Proceedings of Water in Mining 2009, The Australasian Institute of Mining and Metallurgy, Melbourne.
Lock the Gate 2016a, Mine Rehabilitation and Closure Cost: A Hidden Business Risk, viewed 24 July 2016,
Lock the Gate 2016b, Rhetoric vs Reality: A Snap Shot of Progressive Rehabilitation Performance in the Global Mining Industry, viewed 24 July 2016,
McKenzie, NJ, Grundy, MJ, Webster, R & Ringrose-Voase, AJ 2008, Guidelines for Surveying Soil and Land Resources, 2nd edn, CSIRO Publishing, Melbourne.
McCollough, CD & Lund, MA 2006, ‘Opportunities for sustainable mining pit lakes in Australia’, Mine Water and the Environment, vol. 25, iss. 4, pp. 220–226.
Mellar, S, James, G & Chalmers, K 2017, Pre-feasibility Study: Evaluating the Potential to Export Pilbara Solar Resources to the Proposed ASEAN Grid via a Subsea High Voltage Direct Current Interconnector, Report to Pilbara Development Commission, viewed March 12 2018,
Murphy, D & Heyes, J 2016, ‘Mine closure – are we using the right drivers?’, AusIMM Bulletin, October 2016, viewed 12 March 2017,
MWH 2009, Pilbara Integrated Water Supply Pre-Feasibility Study, Perth, viewed 24 August 2018,
Pilbara Development Commission 2015, Pilbara Regional Investment Blueprint, Perth, viewed 24 July 2016,
Pearman, G 2009, 101 Things to do with a Hole in the Ground, Post-Mining Alliance, Cornwall.
Roche, C & Judd, S 2016, Ground Truths: Taking Responsibility for Australia’s Mining Legacies, Mineral Policy Institute, Girrawheen, viewed 24 July 2016,
Standing Council on Energy and Resources 2013, Multiple Land Use Framework, viewed 12 March 2014,
Smyth, CR & Dearden, P 1998, ‘Performance standards and monitoring requirements of surface coal mine reclamation success in mountainous jurisdictions of western North America: a review’, Journal of Environmental Management, vol. 53, pp. 209–229.
Tomaney, J 2010, Place-based Approaches to Regional Development: Global Trends and Australian Implications, Australian Business Foundation, viewed 18 August 2018,
van Gool, D, Tille, P & Moore, G 2005, Land Evaluation Standards for Land Resource Mapping, Resource Management Technical Report 298 3rd Ed, Department of Agriculture, viewed 12 March 2017,




© Copyright 2024, Australian Centre for Geomechanics (ACG), The University of Western Australia. All rights reserved.
View copyright/legal information
Please direct any queries or error reports to repository-acg@uwa.edu.au