Authors: He, K; Swarbrick, G; Sullivan, TD

Open access courtesy of:

DOI https://doi.org/10.36487/ACG_repo/2025_68

Cite As:
He, K, Swarbrick, G & Sullivan, TD 2020, 'Numerical modelling of underground and open pit interaction in a gold mine', in PM Dight (ed.), Slope Stability 2020: Proceedings of the 2020 International Symposium on Slope Stability in Open Pit Mining and Civil Engineering, Australian Centre for Geomechanics, Perth, pp. 1031-1046, https://doi.org/10.36487/ACG_repo/2025_68

Download citation as:   ris   bibtex   endnote   text   Zotero


Abstract:
The Waihi Gold operation (OceanaGold) consists of a mining and milling complex located within the township of Waihi, approximately 125 km southeast of Auckland, New Zealand. Mining at Waihi started in 1878 and comprised both underground mining (1878 to 1952) and open cut mining (1988 to present). The Martha Mine and its immediate environs have experienced a very long period of deformation and subsidence due to the historical underground mining. This study contains an assessment of the potential impacts of the proposed Martha Underground mine on the stability of proposed Martha Phase 4 pit. A 3D numerical model is developed by considering both historical and proposed underground and open cut mining. Caving affected rock mass zones around a planned historical underground caving operation, which has been incorporated into the model. The developed 3D model predicts a response to Martha Underground that is aligned with the experience and previous performance of the Martha Pits in terms of magnitude, location and distribution of movements. Sensitivity analyses were undertaken to investigate the effect of several input parameters used in the study.

Keywords: underground mining, open cut mining, caving zones, numerical modelling

References:
AMC Consultants Pty Ltd. 2007, Site Visit Notes January 2007, unpublished consultant notes of Favona Underground Mine for Newmont Waihi Gold, dated March 2007.
Itasca Consulting Group, Inc. 2019, FLAC2D, version 6.00, computer software, Itasca Consulting Group, Inc., Minneapolis.
Pells Sullivan Meynink Pty Ltd. 2003, 2002‒2003 Geotechnical Investigations Waihi Vol. 1 Text, Plates & Figures, Unpublished consultant report for Newmont Waihi Operations, Report Reference PSM125.R28, dated July 2003.
Pells Sullivan Meynink Pty Ltd. 2005a, Risk Assessment Pumphouse, unpublished consultant report for Newmont Waihi Operations, Report Reference PSM125.R33, dated April 2005.
Pells Sullivan Meynink Pty Ltd. 2005b, Geotechnical Review and Update 2004, unpublished consultant report for Newmont Waihi Operations, Report Reference PSM125.R31, dated January 2005.
Pells Sullivan Meynink Pty Ltd. 2006, Report on Pit Closure Studies, unpublished consultant report for Newmont Waihi Operations, Report Reference PSM125.R34, dated April 2006.
Pells Sullivan Meynink Pty Ltd. 2009a, Site Visit Report February 2009, unpublished consultant report for Newmont Waihi Operations, Report Reference PSM125.L105, dated February 2009.
Pells Sullivan Meynink Pty Ltd. 2009b, South Stability Cutback – Stability Update No. 2, unpublished consultant report for Newmont Waihi Operations, Report Reference PSM125.L106, dated March 2009.




© Copyright 2024, Australian Centre for Geomechanics (ACG), The University of Western Australia. All rights reserved.
View copyright/legal information
Please direct any queries or error reports to repository-acg@uwa.edu.au