DOI https://doi.org/10.36487/ACG_repo/2615_33
Cite As:
Smedley, E, Denholm, E, Lakis, S & Mackenzie, S 2026, 'Common systemic drivers of closure cost underestimation for earthworks', in AB Fourie, G Boggs, J Heyes & M Tibbett (eds),
Mine Closure 2026: Proceedings of the 19th International Conference on Mine Closure, Australian Centre for Geomechanics, Perth, pp. 1-13,
https://doi.org/10.36487/ACG_repo/2615_33
Abstract:
Despite increased scrutiny from regulators, financiers, and stakeholders, mine closure cost estimates continue to systematically underestimate closure costs. This paper examines recurring technical and commercial drivers of underestimation observed across a broad range of mine closure studies, with a focus on rehabilitation earthworks.
Drawing on a review of both internal and third-party closure cost estimates, supplemented by comparisons with measured production and cost data from implemented works, this paper identifies a consistent pattern of optimistic assumptions embedded within many estimates. A major issue is overestimating equipment productivity by relying on standard production values without adjusting for site constraints or considering the specific nature of the work. These assumptions can materially distort unit rates when applied to large‑scale rehabilitation tasks.
This paper also explores the impact of overoptimistic volumetric assumptions, particularly for landform reprofiling and reshaping activities. Simplified geometric models frequently underestimate actual material movements, double handling and trimming losses when compared to surveyed as-built outcomes. In addition, a recurring source of underestimation is the inadequate allowance for indirect costs, including contractor preliminaries, temporary works, supervision, management activities and quality control.
For practitioners, this paper provides a structured lens for stress‑testing closure cost estimates by explicitly linking assumptions to observed cost variance. Rather than advocating for conservatism, the findings highlight where targeted adjustments, validation against measured data, and more transparent treatment of indirect costs can materially improve the defensibility and credibility of closure cost estimates.
Keywords: cost estimation, continual improvement, risk, earthworks
References:
AACE International 2022, Professional Guidance Document 01 – Guide to Cost Estimate Classification Systems, viewed 10 April 2026
Byrne, G 2024, ‘Risks and cost estimates: the disconnect’, in AB Fourie, M Tibbett & G Boggs (eds), Mine Closure 2024: Proceedings of the 17th International Conference on Mine Closure, Australian Centre for Geomechanics, Perth, pp. 47–58,
Caterpillar 2022, Caterpillar Performance Handbook Version 50, Illinois, USA.
Dunow, T & Kalisch, B 2022, 'The high cost of poor closure estimates', in AB Fourie, M Tibbett & G Boggs (eds), Mine Closure 2022: Proceedings of the 15th International Conference on Mine Closure, Australian Centre for Geomechanics, Perth, pp. 1193–1200,
Engineers Australia – Risk Engineering Society 2025, Contingency guideline 3rd Edition, Barton
Espezúa, JM & Vasquez, EL 2023, 'Closure cost estimate—an approach to estimate productivities of main closure activities', in B Abbasi, J Parshley, A Fourie & M Tibbett (eds), Mine Closure 2023: Proceedings of the 16th International Conference on Mine Closure, Australian Centre for Geomechanics, Perth,
International Council on Mining and Metals (ICMM) 2019, Financial Concepts for Mine Closure, London.
Lilford, E 2025, Conceptual Valuation Framework for Unknown Unknowns in Natural Resources, CRC Time, Perth.
Sanders, J, Slingerland, N & Murphy, D 2024, ‘Closing the gap: closure cost estimation trends and pathways to improved maturity’, in AB Fourie, M Tibbett & G Boggs (eds), Mine Closure 2024: Proceedings of the 17th International Conference on Mine Closure, Australian Centre for Geomechanics, Perth, pp. 1149–1162,
SRCE Software 2026, Standardized Reclamation Cost Estimator, version 2.0, computer software,
https://nvbond.org/