Authors: Myers, K; Nahir, M; Gillis, C; Shah, J

Open access courtesy of:

DOI https://doi.org/10.36487/ACG_repo/2315_037

Cite As:
Myers, K, Nahir, M, Gillis, C & Shah, J 2023, 'Clinton creek abandoned mine/interim spillway reclamation project—status of the channel restoration effort', in B Abbasi, J Parshley, A Fourie & M Tibbett (eds), Mine Closure 2023: Proceedings of the 16th International Conference on Mine Closure, Australian Centre for Geomechanics, Perth, https://doi.org/10.36487/ACG_repo/2315_037

Download citation as:   ris   bibtex   endnote   text   Zotero


Abstract:
The Clinton Creek Interim Spillway Reclamation Project is located at the site of the former Clinton Creek Asbestos Mine, about 100 kilometres northwest of Dawson City, Yukon Territory, Canada and about 9 kilometres upstream of the confluence of Clinton Creek and the Forty Mile River. The mine was operated from 1968 through 1978 and extracted approximately 12 million Tonnes of serpentine ore from three open pits. Two waste rock dumps were placed along the south side of Clinton Creek. In 1974 the Clinton Creek Waste Rock Dump experienced a mass failure (a lateral spread) resulting in the blockage of the Clinton Creek channel over a reach length of approximately 700 metres, forming a landslide dam and initiating the formation of a new impoundment named Hudgeon Lake. Upon first filling of the new reservoir, the water discharging from Hudgeon Lake began flowing across the surface of the waste rock dam at the interface between the waste rock and the existing colluvial soil and bedrock of the valley slope to the north. The flow began to incise into the soil and waste rock forming the new alignment of Clinton Creek now displaced hundreds of metres to the north and perched some 25 metres above the former Clinton Creek channel and floodplain. The new channel has gradients ranging from about 3% to 6% and averages about 3.6%. This compares to the channel’s original in regime gradient of 0.075%. Erosion of the new channel at the lake outlet prompted concerns about a breach of the landslide dam and efforts to control erosion of the channel using riprap armor and a rock weir, were began in 1981 However, multiple failures during high flow events resulted in damage and the rebuilding of the erosion protection features over the years. In the spring of 2003, an interim spillway structure to arrest the downcutting in Clinton Creek began construction. The design involved a simple trapezoidal channel with a series of drops constructed using rock filled PVC coated galvanized wire gabion baskets. The upper reaches of this spillway structure have held up reasonably well, but the lower reach below what is referred to as Drop Structure No. 4 has experienced multiple severe erosion/headcutting events over time. Subsequent efforts to arrest erosion and stabilize the channel including an articulated concrete block chute structure have also resulted in failure. This paper will describe current, on-going efforts to provide a stable, functioning interim channel that will provide at least a 50-yr facility life and, in the process, address desired improvements in fish habitat and fish migration issues until a final, permanent solution can be funded, designed, and constructed.

References:
Advisian (Subsidiary of Worley Parsons Group), 2015, Clinton Creek Drop Structure No. 4 Repair, December 2015.
BGC Engineering, Inc., 2016, Government of Yukon, Clinton Creek, Independent Engineer’s Channel Assessment, October 31, 2016.
Chilkoot Geological Engineers LTD, 2015, Borrow Source Assessment, 2015.
Jacobs Engineering Group Inc., 2019, Memorandum Report, Clinton Creek Mine, Review of Drop Structure #4 Failure, April 5, 2019.
Jacobs Engineering Group Inc., 2019, Memorandum Report, Clinton Creek Mine, DS4 Interim Improvement Options, April 5, 2019.
Myers, K. L., 2015, ‘Stream Relocation and Geomorphic Design to Improve Sustainability’, Proceedings of Mine Water Solutions in Extreme Environments, April 12-15, 2015, Vancouver, Canada.
Parsons, Inc., Clinton Creek Mine Site, Drop Structure 4 Options Assessment and Detailed Engineering, Design Options Evaluation Report. October 25, 2021.
Parsons, Inc., Design Flow Manual, Clinton Creek Mine Site, Drop Structure 4 Repair Project, April 16, 2023.
Parsons, Inc., Technical Memorandum, Field Investigation Results, February 15, 2023.
Rosgen, David, Applied River Morphology, Wildland Hydrology, 1996.
Tetra Tech Canada Inc., 2019, Field Inspection Memo, DS4 Emergency Repairs Followup Inspection, Long-Term Performance Monitoring Program – Clinton Creek Mine, Yukon, October 15, 2019.
UMA Engineering Ltd., Abandoned Clinton Creek Asbestos Mine, Condition Assessment Report, April 2000.
UMA Engineering Ltd., 2000, Abandoned Clinton Creek Asbestos Mine, Risk Assessment Report, April 2000.
UMA Engineering Ltd., 2003, Clinton Creek Channel Stabilization (Stage 1) Construction Report, April 2003.
UMA Engineering Ltd., 2003, Clinton Creek Channel Stabilization (Stage 2) Construction Report, December 2003.
UMA Engineering Ltd., 2005, Clinton Creek Channel Stabilization (Stage 3) Construction Report, February 2005.
Wingrove, T. R. et. al., 2011, ‘Former Clinton Creek asbestos mine’, Mine Closure 2011, Alberta, Canada, pg 489 – 500.
Wolman, M. G., ‘A method of sampling coarse river bed material’, Transactions of American Geophysical Union 35, pg 951 – 956, December 1954.
Wood Canada Ltd., 2019, Clinton Creek Remediation Project, Dam Breach Assessment, November 15, 2019.
Wood Canada Ltd., 2019, Geotechnical Summary, December 2019.
Worley Parsons Canada, 2015, Clinton Creek Engineering Review and Assessment. Part 1, March 31, 2015.




© Copyright 2024, Australian Centre for Geomechanics (ACG), The University of Western Australia. All rights reserved.
View copyright/legal information
Please direct any queries or error reports to repository-acg@uwa.edu.au