Authors: Voyer, E; Arsenault, J

Open access courtesy of:

DOI https://doi.org/10.36487/ACG_repo/2615_32

Cite As:
Voyer, E & Arsenault, J 2026, 'Rehabilitation of historical mine features: from mitigation toward true risk elimination', in AB Fourie, G Boggs, J Heyes & M Tibbett (eds), Mine Closure 2026: Proceedings of the 19th International Conference on Mine Closure, Australian Centre for Geomechanics, Perth, pp. 1-15, https://doi.org/10.36487/ACG_repo/2615_32

Download citation as:   ris   bibtex   endnote   text   Zotero


Abstract:
The Abitibi–Northern Ontario region is one of the most historically significant mining areas in Canada, with more than a century of continuous mineral exploration, underground development, and large-scale mining production. Hundreds of historical mine workings are the legacy of extensive exploration and mining operations, including shafts, raises, portals, drifts, adits and stopes, often connected in complex underground networks. Over time, these mine features have become part of the regional landscape. Closure and rehabilitation work can be critical, as unmanaged legacy mine hazards may continue to deteriorate and present significant hazards that can affect ground integrity and community safety. Initial mitigation approaches often focus on containing risks rather than managing the underlying sources of hazards. Advantages to proceeding towards comprehensive, integrated, long-term interventions that aim at eliminating hazards rather than mitigating them include enabling future access to communities, reducing long-term costs and improving the likelihood of relinquishment. Eliminating hazards may require several investigations and design steps, as it is often more complex and costly than short- or medium-term securing measures and therefore requires strong justification before being implemented. However, historical mining activities were often poorly documented, lack reliable records, and deterioration over time makes it necessary to verify subsurface conditions. Rehabilitation designs of legacy mine hazards start with desktop assessment using sometimes limited historical records to identify potential risks. Field investigations using various survey techniques, along with technical assessments that meet regulatory standards, enable initial assumptions to be refined to design tailored rehabilitation options. This article presents case studies of completed and ongoing rehabilitation projects in the Abitibi–Northern Ontario region. It outlines both industry and technical perspectives on the challenges posed by limited historical information, considerations guiding the selection of investigation methods and the field constraints encountered during investigation and rehabilitation processes. It demonstrates that effective rehabilitation aimed at eliminating hazards relies on an adaptive, risk-based approach that evolves as new information emerges, ensuring hazards are accurately characterised and properly addressed.

References:
Carter, TG & Miller, RI 1995, ‘Crown pillar risk assessment – cost effective measures for mine closure remediation planning’, Transactions of the Institution of Mining and Metallurgy, vol. 104, pp. A41–A57.
Carter, TG, Cottrell, BE, Carvalho, JL & Steed, CM 2008, ‘Logistic regression improvements to the scaled span method for dimensioning surface crown pillars over civil or mining openings’, Proceedings of the 42nd US Rock Mechanics Symposium, ARMA.
Carter, TG 2014, ‘Guidelines for use of the scaled span method for surface crown pillar stability assessment’, Proceedings of the 1st International Conference on Applied Empirical Design Methods in Mining, Lima.
Dubé & Langevin, 2020, ‘Gold in the Abitibi Greenstone Belt, Canada: a Geological and Historical Overview, Magazine Ressources Mines et Industries, vol.1, no.2.
Geotech Ltd. 2026, Abitibi Greenstone Belt, viewed 30 April 2026,
Golder Associates 1992, Internal Report, Report 911‑1720.
Golder Associates 2007, Internal Report, Ref. No. 007-1227-0014.
Mathews, KE, Hoek, E, Wylie, DC & Stewart, SBV 1981, Prediction of Stable Excavation Spans for Mining at Depths Below 1,000 Metres in Hard Rock, CANMET Report DSS Serial No. OSQ80‑00081.
Nickson, SD 1992, Cable Support Guidelines for Underground Hard Rock Mine Operations, MASc thesis, The University of British Columbia, Vancouver.
Potvin, Y 1988, Empirical Open Stope Design in Canada, PhD thesis, The University of British Columbia, Vancouver.
Potvin, Y & Milne, D 1992, ‘Empirical cable bolt support design’, Proceedings of Rock Support in Mining and Underground Construction, AA Balkmema, Rotterdam, pp. 269–275.
Stewart, CHE 1947, Limited: Report on the Property, Ref. no. GM00227.
WSP 2025a, Internal Technical Memorandum, Ref. no. 001‑CA0043795.3532‑4000‑TM‑Rev0.
WSP 2025b, Internal Technical Memorandum, Ref. no. 007‑CA0043795.3532‑5000‑TM‑RevA.
WSP 2025c, Internal Report, Ref. No. 20138040-027-R-RevA.
WSP 2026a, Internal Report, Ref. no. CA0043795.3532‑009‑R‑RevA‑5000.
WSP 2026b, Internal Technical Memorandum, Ref. no. 005‑CA0058390.9618‑TM‑RevA.




© Copyright 2026, Australian Centre for Geomechanics (ACG), The University of Western Australia. All rights reserved.
View copyright/legal information
Please direct any queries or error reports to repository-acg@uwa.edu.au